9.2 16L/34R Runway Remediation

The runway remediation plan for 16L/34R will take place commencing 07 NOV 2025 and will be split in to three phases, running up to 13 JUN 2026.

Phase Start Date End Date Summary
Phase 1 07 NOV 2025 1601z 14 JAN 2026 2359z Works between A and A2. RWY 16L/34R will operate with reduced length as a non precision runway
Phase 2 15 JAN 2026 0000z 12 APR 2026 2359z Works between A9 and A12. RWY 16L/34R will operate with reduced length as a non precision runway
Phase 3 13 APR 2026 0000z 13 JUN 2026 2359z Full closure of RWY 16L/34R

These phases are detailed below along with adjusted SOP relating to the operation of 16L/34R

9.2.1 Phase 1

The length of RWY 16L/34R will be reduced to 4270m. The vast majority of aircraft on normal operations will be able to depart using this runway length.

34R Operations: A2 becomes "full length" for departures, with A3 available as an intersection at the controller's discretion. Temporary arrival procedure RNP T 34R is available and can be found in the AIP Supplement and on Navigraph charts.

16L Operations: The last point at which an aircraft can vacate is A2. Intersections available as normal.

9.2.2 Phase 2

The length of RWY 16L/34R will be reduced to 3030m. The majority of aircraft should still be able to depart from this runway length, however in the event that they are unable, 16R/34L should be used as the alternative.

9.2.3 Phase 3

RWY 16L/34R will be closed for an extended period, with all departures/arivvals utilising RWY 16L/34R.

9.3 Revised Procedures

9.3.1 Phase 1

9.3.1.1 Arriving Aircraft

When arriving 34R, pilots can expect the temporary RNP T 34R approach which accommodates the displaced threshold. This procedure is active from 07 NOV 2025 0000z until 18 MAR 2026 2359z.

9.3.1.2 Departing Aircraft

Departing traffic will be instructed to hold short taxiway A2 on either B or C and GMC should hand off traffic at the earliest opportunity to AIR to allow for appropriate sequencing to take place.